Maintenance work in the crawl space

Over the coming period, maintenance work will be carried out in the crawl space in some of the buildings at Campus Lappis. The work is done to ensure that the buildings continue to maintain a good standard and can be used by many generations of students in the future.

The work is planned to start on 30 may and is expected to be completed by 3 july. The work will take place in stages, and each building is expected to take approximately two weeks to complete. Below you can see a preliminary schedule for when the work is planned to start at each address.

During this period, disturbing noise may occur. The contractor will work on weekdays between 07:00–16:00, but no disturbing noise will occur before 08:00.

As part of the work, the contractor will set up temporary fenced work areas at the buildings where work is taking place. These are required to ensure a safe work environment and will not affect accessibility in the area.

Preliminary schedule

Forskarbacken 7: 1 april –15 april
Forskarbacken 19: 14 april – 18 may
Forskarbacken 21:  4 april- 18 may
Forskabcken 10, Amanuensvägen 3: 18 maj- 5 juni
Forskarbcken 12, Amanuensvägen 5: 5 juni-12 juni
Amanuensvägen 10: 12 juni- 3 july

The schedule is preliminary and may be adjusted depending on how the work progresses.